Revolutionizing Industry Speed! Vanke Shenyang Xichen Zhiguang Sales Office Achieved Completion and Opening in Just 60 Days—Setting a New Record Within the Vanke System
Recently, the Shenyang Vanke Xichen Zhiguang sales office project was successfully completed and officially opened. It took only 60 days from groundbreaking to full debut, not only breaking the record for the construction speed of sales offices in Shenyang, but also creating a new high for construction speed within the national Vanke system. With the innovative mode of steel structure assembly+100% dry construction, it demonstrates Vanke's technical strength and efficient execution ability in the field of construction industrialization. It is reported that the project is located in Shenyang Tiexi Economic and Technological Development Zone. As the core supporting project of Vanke Xichen Zhiguang Residential Project, the sales office takes "efficiency, high quality, and green" as the construction core, adopts a steel structure main system, and is equipped with three core components: steel frame lightweight floor panels, prefabricated roof panels, and prefabricated daughter wall panels. The entire process implements 100% dry operation, completely breaking free from the limitations of traditional wet operation and achieving a dual breakthrough in construction efficiency and engineering quality.
Amazing speed! Multiple construction milestones refresh industry benchmarks
The most eye-catching highlight of the project is its extreme construction speed. A series of key node data demonstrate the hardcore strength of prefabricated construction: the installation of the 400 ton steel structure main body only takes 11 days, and the construction of the 3800 ㎡ curtain wall double-layer cable-stayed ceramic rod structure only takes 23 days. Ultimately, it achieved an astonishing result of 60 days from groundbreaking to official opening, which is nearly 60% shorter than the conventional construction period of more than 150 days for traditional sales offices, setting a new peak in the construction speed of sales offices within the national Vanke system. Among them, the rapid construction of the 3800 ㎡ curtain wall double-layer cable-stayed ceramic rod structure is particularly impressive. This structure has a delicate design and high construction difficulty. Similar to ceramic rod curtain walls, it is widely used in large public buildings, but it is not common to efficiently land in short-term projects such as sales offices. The project team drew on advanced curtain wall construction experience and used BIM 3D software for detailed design and construction simulation, accurately controlling the installation accuracy of each ceramic rod and each group of cables. Through the optimization process of "ground partition assembly+segmented tensioning", while ensuring construction quality, the construction efficiency was greatly improved, and all installations were completed in just 23 days, demonstrating superb construction technology level.
Core construction system: steel structure+dry construction, laying a solid and efficient foundation
The rapid implementation of the project relies on the support of core construction technology. The main structure adopts a steel frame system, and the load-bearing components such as steel columns and beams are standardized and prefabricated in the factory. High quality steel that meets industry standards is selected, and the cutting, welding, rust removal, painting and other processes strictly follow the specifications. The precision of the components is controlled at the millimeter level, and only high-strength bolts are needed for precise connection on site, without the need for on-site welding and wet pouring. This not only ensures the stability and seismic resistance of the structure, but also lays the foundation for rapid construction. In terms of enclosure and floor system, the project adopts three major prefabricated components: steel framed lightweight floor panels, prefabricated roof panels, and prefabricated daughter wall panels. All components are prefabricated in the factory and assembled on site. Among them, the steel framed lightweight floor panel has a light weight and high strength, and can be directly hoisted and spliced on site without the need for formwork and concrete pouring; Prefabricated roof panels and daughter wall panels integrate multiple functions such as insulation and waterproofing, replacing traditional brick masonry and cast-in-place processes, significantly reducing on-site work processes. At the same time, the project will implement 100% dry operation throughout the entire process, completely abandoning wet operations such as concrete pouring, mortar plastering, and on-site maintenance. The construction process will be simplified to "factory prefabricated components → transportation to the site → hoisting and positioning → bolt fastening → finished product protection", with no waiting period for maintenance, no sewage discharge, and no large amount of construction waste accumulation. This construction mode not only conforms to the concept of green and low-carbon construction, but also eliminates the dependence on water sources, temperature, and humidity, adapts to the low-temperature climate characteristics of Shenyang in winter, ensures that the construction progress is not affected by seasons, and provides a key guarantee for the 60 day rapid opening.
Industry significance: Establishing a new model for the construction of prefabricated sales offices
The successful implementation of the Shenyang Vanke Xichen Zhiguang sales office project not only seized the marketing window period for the Vanke Xichen Zhiguang residential project in advance, but also helped the smooth implementation of the project's subsequent sales promotion work, and set a new example of efficient construction of prefabricated sales offices in the industry. As the sales office project with the fastest construction speed within the national Vanke system, its innovative practice further verifies the adaptability and superiority of the steel structure assembly+100% dry construction mode in short cycle, high demand buildings. It is reported that Vanke Xichen Zhiguang Residential Project is located in the core area of Tiexi Economic and Technological Development Zone, mainly promoting three bedroom units of 96-123 square meters. With Vanke's brand influence and high-quality product strength, it has attracted market attention. The rapid opening of the sales office this time not only enhances the market exposure and brand reputation of the project, but also allows buyers to experience the construction strength and quality standards of the project in advance. Industry insiders say that the construction speed and technological application of this project provide replicable and promotable solutions for the construction of sales offices and temporary commercial buildings in Shenyang and even northern regions, promoting the extension of prefabricated building technology from residential areas to commercial supporting scenarios, helping the construction industry transform and upgrade towards industrialization, greening, and efficiency, and also demonstrating Vanke's responsibility and commitment in promoting the development of construction industrialization. In the future, Vanke will continue to deepen the research and application of prefabricated building technology, inject new vitality into urban development through more efficient and high-quality construction practices, and provide consumers with more high-quality building products and services.